SITE
NEWS August 18 2020

Liquidated Damages in Construction Contracts/Disputes

By Danielle O'Brien, Junior Associate

 

Construction contracts almost always contain a liquidated damages clause allowing the employer to claim compensation for a contractor’s failure to progress the works pursuant to set milestones.

Liquidated damages clauses are a typical instrument in construction contracts, both in civil and common law jurisdictions. UAE legislation and jurisprudence illustrates that the legal position in the UAE differs from common law jurisdictions.

Unsurprisingly, many international developers and contractors are unsure of the enforceability of liquidated damages clauses in the UAE, and consequently remain uneasy when a resulting claim arises.

The purpose of this article to alleviate some of this uncertainty by setting out a courts options when determining a contractor’s liability thereunder.

 

What are Liquidated Damages?

Liquidated damages are a sum of money – often calculated by way of a formula – that can be recovered if a party breaches their obligations under the contract. The sum (or the method to calculate such sum) must be expressly agreed upon by the parties at the time of entering into the contract and should be a good faith attempt at predicting the extent of actual damages that could be suffered by a party (e.g. the employer in construction contracts).

Liquidated damages clauses usually apply to a specific type of contractual breach, for example, in construction contracts the breach is typically a delay in completion.

Such limitation of liability is recognised and valid pursuant to Article 390(1) of Federal Law 5/1985 (the “Civil Code”).

1-The two contracting parties may fix, in advance, the amount of damages either in the contract or in a subsequent agreement subject to the law provisions.

2-The judge may, in all cases, at the request of one of the parties, amend such an agreement, in order to make the amount assessed equal to the prejudice. Any agreement to the contrary is void.

Liquidated damages are recognised under UAE law and are upheld by courts and arbitral tribunals in the UAE.

A liquidated damages clause obliges a contractor to pay an agreed amount in the event of a delay in the execution of the agreed work. It is a penalty requirement in accordance with Article 390 of the Civil Transactions Law.

[Dubai Court of Cassation 167/2005]

 

FIDIC Form of Contract

Construction contracts are frequently based on standardised clauses stemming from the Fédération Internationale Des Ingénieurs – Conseils (“FIDIC”).

Sub-clause 8.7 of the FIDIC Yellow Book sets out the following clause:

If the Contractor fails to comply with [Time for Completion], the Contractor shall subject to [Employer’s Claims] pay delay damages to the Employer for this default. These delay damages shall be the sum stated in the Appendix to Tender, which shall be paid for every day which shall elapse between the relevant [Time for Completion] and the date stated in the Taking-Over Certificate. However, the total amount due under this Sub-Clause shall not exceed the maximum amount of delay damages (if any) stated in the Appendix to Tender.

These delay damages shall be the only damages due from the Contractor for such default, other than in the event of termination under Sub-Clause 15.2 [Termination by Employer] prior to completion of the works. These damages shall not relieve the contractor from his obligation to complete the works, or from any other duties, obligations or responsibilities which he may have under the Contract. (emphasis added)

As seen above, liquidated damages clauses often also provide for a cap on a party’s liability. While this is beneficial to the party allegedly in breach of its contractual obligations, such cap may limit an aggrieved party from recovering the full amount of its losses (such as loss of profits).

 

Claiming Liquidated Damages

A party claiming damages must satisfy a tripartite test to establish a claim for compensation under UAE law, namely:

a.            a loss;

b.            a wrongful act (i.e., contractual breach); and

c.            causation.

These three elements are well founded in UAE jurisprudence. As set out by the Court of Cassation:

It is well established by this Court that the liability, whether it is contractual or tortious, cannot materialise unless all of its three elements: breach/tort, damages and causality/the link between the damage and the breach/tort, are met. The compensation cannot be awarded unless all the elements are met.  As a result, it is not sufficient to hold the respondent liable and order it to pay compensation accordingly materialisation of the element of the breach/tort alone without proving the element of the damage.  The burden of proof of the alleged damages lies upon the creditor.

 [Court of Cassation Case No. 153 of 2011, issued on 10 June 2012]

A claim for liquidated damages is no exception and must meet the aforementioned tripartite test. However, an important distinction must be made; when parties contract into a liquidated damages clause, the creditor need not prove the extent, or even the occurrence of damages (UAE 264/2011). Instead, the burden of proof shifts to the defendant, who must prove that the claimant did not suffer damages (at all, or to the extent provided for in the liquidated damages clause) (UAE 187/2016).

When a party founds its claim on a liquidated damages clause, a court has three options:

1.       Uphold the clause;

2.       Amend the clause; or

3.       Render the clause unenforceable.

 

1.       Upholding Liquidated Damages Clauses

When upholding a liquidated damages clause, the court will undoubtably interpret the clause in order to ascertain its applicability.

Articles 265 and 266 of the Civil Code state the following:

Article 265

1-When the wording of a contract is clear, it cannot be deviated from in order to ascertain by means of interpretation the intention of the contracting parties.

2- Where the contract has to be construed, it is necessary to ascertain the common intention of the contracting parties and to go beyond the literal meaning of the words, taking into account the nature of the transaction as well as that loyalty and confidence which should exist between the parties in accordance with commercial usage.

Article 266

1-In cases of doubt, the construction shall be in favour of the debtor.

2-The construction, however, of obscure expressions in adhesion contracts must not be detrimental to the adhering party.

It therefore follows that, if a contractual clause is clear, a court will interpret it in an effort to follow the literal meaning. Alternatively, if there is ambiguity as to the contractual clause, a court may look to the parties’ mutual intention and conduct to decipher the true meaning of the clause.

Accordingly, if the liquidated damages clause specifically cites the type of breach and the preestablished formula or affixed quantum to be paid by the defaulting party, the court is likely to uphold the clause.

 

2.       Amending Liquidated Damages Clauses

Another option that courts have in the UAE is to amend a liquidated damages clause (either decreasing or increasing the sum to be paid by the defaulting party). This is a highly controversial point for common law practitioners.

While Court of Cassation judgements are not binding, they are highly persuasive and are often followed by lower courts. Ultimately, the trial judge has discretion in making the assessment of whether the harm actually occurred, and if the trial judge assesses that there is no breach, there can be no claim.

The Court of Cassation in Case No. 138/94 confirmed its power to reduce the amount of compensation provided for in the liquidated damages clause. The Court of Cassation further stated that it has a wide discretion and may balance the actual loss suffered against the total amount provided for in the liquidated damages clause. One can argue that this is to ensure that the liquidated damages clause is fair, rather than punitive.

Trends in jurisprudence suggest that courts are only inclined to exceed a limitation of liability in certain exceptional circumstances.

A liquidated damages clause may be amended by a judge in exceptional circumstances, at the request of a party. The burden of proving that the compensation sought exceeds the damage, is that of the injured.

[Dubai Court of Cassation 48/2005 and 65/2005]

As such, the very nature of a liquidated damages clause is to protect an employer from foreseeable damages. The courts have been reluctant to increase a liquidated damages clause in the absence of exceptional circumstances. Accordingly, an employer will not likely be able to claim liquidated damages in excess of other claims, such as loss of profits.

 

3.       Rendering Liquidated Damages Clauses Unenforceable

A contractor seeking to strike down a liquidated damages clause will be comforted to know that the courts also have the power to render a liquidated damages clause unenforceable in the following two circumstances:

a)       the claimant’s failure to establish its entitlement to liquidated damages (i.e. a contractual breach); and

b)      the termination of the primary obligation.

As ancillary contractual obligations, when a contract is terminated, the resulting obligations under the liquidated damages clause essentially fall away. Accordingly, if the contract has been terminated the contractor need not meet the upcoming set milestones, and the employer would not be able to claim liquidated damages from the date of termination of the contract.

 

Conclusion

It is evident that legislation permits the enforceability of liquidated damages clauses, and courts are content in upholding them.

Trends in jurisprudence are far more telling - when a claim for liquidated damages is brought before a court, the court has discretion in deciding whether it will uphold, amend or revoke the clause. Therefore, unlike in common law jurisdictions, a claim for liquidated damages is not a straightforward one. Employers who have suffered damages in excess of the liquidated damages cap can request a court to amend the clause, allowing for greater compensation. Conversely, a contractor can also attempt to evidence that the employer suffered little to no damage, thereby ultimately decreasing the contractor’s liability under the liquidated damages clause, or (and a more appealing option) seek to rescind the liquidated damages clause in its entirety.

You might also be interested in...
NEWS January 28 2021
Tortious Interference in UAE Law
NEWS November 02 2020
Financing An International Trade
NEWS October 04 2020
DIFC’s Data Protection Law
NEWS June 30 2020
Public Prosecution in Dubai
NEWS June 22 2020
Covid-19 & Force Majeure
NEWS June 15 2020
Use of Electronic Signatures
NEWS May 04 2020
Piercing the Corporate Veil
NEWS January 16 2020
Bona Fide Principle Prevails
NEWS September 04 2018
Franchising in the UAE
NEWS November 14 2018
Extradition Requests in the UAE
NEWS April 24 2018
Bankruptcy in the UAE
NEWS February 07 2018
Seminar: UAE Civil Procedures Law
NEWS March 19 2018
Recent Developments at the RDC
NEWS August 01 2018
Charities and Endowments in Dubai
NEWS September 17 2017
Our Litigation Team Award Winners
NEWS December 05 2022
Interest on Late Payments in the UAE

For better web experience, please use the website in portrait mode